The Secret Of ISEB ISEB-SWT2 Free Practice Exam
It is more faster and easier to pass the ISEB ISEB-SWT2 exam by using Simulation ISEB ISTQB-ISEB Certified Tester Foundation Level questuins and answers. Immediate access to the Abreast of the times ISEB-SWT2 Exam and find the same core area ISEB-SWT2 questions with professionally verified answers, then PASS your exam with a high score now.
Online ISEB-SWT2 free questions and answers of New Version:
NEW QUESTION 1
A system calculates the amount of customs duty to be paid:
_ No duty is paid on goods value up to, and including, $2,000.
_ The next $8,000 is taxed at 10%.
_ The next $20,000 after that is taxed at 12%.
_ Any further amount after that is taxed at 17%.
To the nearest $, which of these groups of numbers fall into three DIFFERENT equivalence classes?
- A. A.-$20,000 $20,001 $30,001B.$2,000 $2,001 $10,000C.$2,000 $8,000 $20,000
- B. $1,500 $2,000 $10,000
Answer: C
NEW QUESTION 2
Boundary value testing:
- A. Is the same as equivalence partitioning tests
- B. Test boundary conditions on, below and above the edges of input and output equivalence classes
- C. Tests combinations of input circumstances
- D. Is used in white box testing strategy
Answer: B
NEW QUESTION 3
What do static analysis tools analyze?
- A. Design
- B. Test cases
- C. Requirements
- D. Program code
Answer: D
NEW QUESTION 4
Which of the following is a white box testing design characteristic?
- A. To be based on specifications
- B. To be based on an analysis of the test basis documentation
- C. To be based on an analysis of the structure of the component or system
- D. To include both functional and non-functional testing
Answer: C
NEW QUESTION 5
Which of the following statements is most true about test conditions?
- A. An item or event of a component or system that can be verified by one or more test cases.
- B. The grouping of a composite set of test cases which, when tested as a whole, reveal a positive or negative result.
- C. A testable component derived from business requirements.
- D. Applies to software testing only.
Answer: A
NEW QUESTION 6
Which of the following are aids to good communication, and which hinder it?
- A. Try to understand how the other person feels.i
- B. Communicate personal feelings, concentrating upon individuals.ii
- C. Confirm the other person has understood what you have said and vice versa.i
- D. Emphasize the common goal of better quality.
- E. Each discussion is a battle to be won.
- F. (i), (ii) and (iii) aid, (iv) and (v) hinder.
- G. (iii), (iv) and (v) aid, (i) and (ii) hinder.
- H. (i), (iii) and (iv) aid, (ii) and (v) hinder.
- I. (ii), (iii) and (iv) aid, (i) and (v) hinder.
Answer: C
NEW QUESTION 7
The test improvement project will take place in an organization developing a safety-critical avionics application. Which one of the following standards do you believe would be most appropriate to take into account for compliance during your assignment? 1 credit
- A. ISO 9126
- B. IEEE 829
- C. BS 7925/2
- D. DO-178B
Answer: D
NEW QUESTION 8
Debugging and Testing are key activities in the software development lifecycle. Which of the following are 'Debugging' activities?
* a) Identifying, a failure
* b) Locating the cause of failure
* c) Fixing the defect
* d) Checking the fix has resolved the failure
- A. a & d
- B. a & b
- C. b & c
- D. c & d
Answer: A
NEW QUESTION 9
Functional and structural tests are alternative test types that may be used separately or together at which test level? [K1]
- A. At the component test level only
- B. At all test levels
- C. At integration testing and system testing levels only
- D. At all levels from integration testing to acceptance testing
Answer: B
NEW QUESTION 10
As part of the improvement program, the organization is also looking at tool support. Which type of tool could be used to ensure higher quality of the code to be reviewed? 1 credit
- A. Review tool
- B. Test execution tool
- C. Static analysis tool
- D. Test design tool
Answer: C
NEW QUESTION 11
Which type of review has the following main purposes:
discussing, making decisions, evaluating alternatives, finding defects, solving technical problems and checking conformance to specifications, plans, regulations, and standards?
- A. Technical Review
- B. Inspection
- C. Walkthrough
- D. Informal review
Answer: A
NEW QUESTION 12
Risks should be constantly reviewed. Given the current situation, which one of the following factors is most likely to lead to a revised view of product risk? 3 credits
- A. The concerns over the user interface may lead to changes to the interface which cannot be implemented by development in time for the second test iteration.
- B. The concerns over the user interface raises the likelihood of a risk in that area and increases the amount of test effort needed for the user interface, thereby limiting the test effort available for other parts of the test management tool.
- C. The delivery of the application without the interface changes may upset the user community.
- D. The method used for test estimation is not accurate enough and hence the money spent on testing exceeded its budget.
Answer: B
NEW QUESTION 13
Security falls under..?
- A. compliance testing
- B. disaster testing
- C. verifying compliance to rules
- D. functional testing
- E. ease of operations
Answer: A
NEW QUESTION 14
In a system designed to work out the employee tax to be paid:
_ An employee has $4,000 of salary tax free.
_ The next $1,500 is taxed at 10%.
_ The next $28,000 after that is taxed at 22%.
_ Any further amount is taxed at 40%.
Which of these is a valid Boundary Value Analysis test case?
- A. $28,000B.-$1,500C.$33,501D.$5,000
Answer: C
NEW QUESTION 15
What is the value of static code analysis?
- A. Detection of failures not easily found by other types of testing
- B. Early defect detection
- C. Detection of suspicious operations caused by deviations from regulations
- D. Detect deviations in standards by executing the source code
Answer: B
NEW QUESTION 16
Which of the following statements about risks is most accurate?
- A. Project risks rarely affect product risk.
- B. Product risks rarely affect project risk.
- C. A risk-based approach is more likely to be used to mitigate product rather than project risks.
- D. A risk-based approach is more likely to be used to mitigate project rather than product risks.
Answer: C
Explanation:
In general, project risk and product risk can be hard to differentiate. Anything that impacts on the quality of the delivered system is likely to lead to delays or increased costs as the problem is tackled. Anything causing delays to the project is likely to threaten the delivered system's quality. The risk-based approach is an approach to managing product risk through testing, so it impacts most directly on product risk.
NEW QUESTION 17
What is the Risk Priority Number for risk item number 2? 2 credits
- A. 16
- B. 2
- C. 1
- D. 63
Answer: D
NEW QUESTION 18
Which of the following is a valid drawback of independent testing? 1 credit
- A. Developer and independent testing will overlap and waste resources.
- B. Developers loose the sense of responsibility and independent testers may become a bottleneck.
- C. Independent testers need extra education and always cost more.
- D. Independent testers will become a bottleneck and introduce problems in incident management.
Answer: B
NEW QUESTION 19
Which option is part of the ‘implementation and execution’ area of the fundamental test process?
- A. Developing the tests.
- B. Comparing actual and expected results.
- C. Writing a test summary.
- D. Analyzing lessons learnt for future releases.
Answer: B
Explanation:
* A. is part of ‘Analysis and design’.
* C. is part of ‘Evaluating exit criteria and reporting’.
* D. is part of ‘Test closure activities’.
NEW QUESTION 20
Which of the following would NOT be a typical target of testing support tools?
- A. Automate activities that require significant resources when done manually
- B. Automate activities that cannot be executed manually
- C. Automate repetitive tasks
- D. Automating repetitive inspections
Answer: D
NEW QUESTION 21
The effect of testing is to:
- A. Increase software quality;
- B. Give an indication of the software quality;
- C. Enable those responsible for software failures to be identified;
- D. Show there are no problems remaining?
Answer: B
NEW QUESTION 22
A test log is one of the documents that need to be produced in this domain in order to provide evidence of testing. However, the level of detail of test logs can vary. Which of the following is NOT an influencing factor for the level of detail of the test logs being produced? 1 credit
- A. Level of test execution automation
- B. Test level
- C. Regulatory requirements
- D. Experience level of testers
Answer: D
NEW QUESTION 23
Which of the following would be the most significant input to estimating the time to carry out the specified testing tasks? 3 credits
- A. The skills and experience of developers to correct the failures.
- B. The standards used for the requirements specification.
- C. The metrics recorded from testing the capture-replay tool.
- D. The number of testers in the company and their grade.
Answer: C
NEW QUESTION 24
A number of options have been suggested for the level of independence to be employed for the testing on the next project, and are shown below.
- A. External test specialists perform non-functional testing.i
- B. Testing is outsourced.ii
- C. Testing is carried out by the developer.i
- D. A separate test team carries out the testing.
- E. Testing is performed by the business.v
- F. Testing is performed by a different developer.Which of the following orders the above in a correct order of independence? 1 credit
- G. i, ii, iv, vi
- H. ii, i, v, vi
- I. ii, v, i, iii
- J. i, iv, v, vi
Answer: B
NEW QUESTION 25
Which statement BEST describes when test planning should be performed? [K1]
- A. Test planning is performed only once, at the beginning of the life cycle, andgenerates a Master Test Plan
- B. Test planning is performed at the beginning of the life cycle and again at the beginning of test execution
- C. Test planning is performed at the beginning of the life cycle and again at every test level
- D. Test planning is performed continuously in all life cycle processes and activities
Answer: D
NEW QUESTION 26
Which of the following is a Black Box test design technique?
- A. Decision Coverage
- B. Error Guessing
- C. Statement Coverage
- D. Equivalence Partitioning
Answer: D
NEW QUESTION 27
Which of the following characteristics is most likely to promote effective software testing? [K1]
- A. Independence from the production process
- B. A belief that programmers always make mistakes
- C. Knowledge of the number of defects typically found in a program
- D. Confidence that the next stage will find defects missed at this stage
Answer: A
NEW QUESTION 28
Which is not in sequence in 11 Step Software Testing process..?
- A. Assess development plan and status
- B. Develop the test plan
- C. Test software design
- D. Test software requirement
Answer: C
NEW QUESTION 29
One of the roles in a review is that of moderator, which of the following best describes this role?
- A. Plans the review, runs the review meeting and ensures that follow-up activities are completed.
- B. Allocates time in the plan, decides which reviews will take place and that the benefits are delivered.
- C. Writes the document to be reviewed, agrees that the document can be reviewed, and updates the document with any changes.
- D. Documents all issues raised in the review meeting, records problems and open points.
Answer: A
NEW QUESTION 30
Which of the following is not a type of incremental testing approach?
- A. Top down
- B. Big-bang
- C. Bottom up
- D. Functional incrementation.
Answer: B
NEW QUESTION 31
......
P.S. Easily pass ISEB-SWT2 Exam with 120 Q&As Thedumpscentre.com Dumps & pdf Version, Welcome to Download the Newest Thedumpscentre.com ISEB-SWT2 Dumps: https://www.thedumpscentre.com/ISEB-SWT2-dumps/ (120 New Questions)