we provide Accurate GAQM CLSSGB sample question which are the best for clearing CLSSGB test, and to get certified by GAQM Certified Lean Six Sigma Green Belt (CLSSGB). The CLSSGB Questions & Answers covers all the knowledge points of the real CLSSGB exam. Crack your GAQM CLSSGB Exam with latest dumps, guaranteed!

Check CLSSGB free dumps before getting the full version:

NEW QUESTION 1
While management of a company must set the stage for all improvement efforts, which of these 5S’s is primarily driven by management?

  • A. Straighten
  • B. Sort
  • C. Shine
  • D. Sustain

Answer: D

NEW QUESTION 2
The Central Limit Theorem helps us understand the __________ we are taking and is the basis for using sampling to estimate population parameters.

  • A. Analysis
  • B. Kurtosis
  • C. Risk
  • D. Route

Answer: C

NEW QUESTION 3
Lean focuses on the sequence of activities and work required to produce a product or a service. This flow is called a __________.

  • A. Value-add Flow
  • B. Production Map
  • C. Value Stream
  • D. Operating Procedure

Answer: C

NEW QUESTION 4
When two Inputs have an impact on the Output together yet seem to have no or little impact on their own this is called a/an __________.

  • A. Interaction
  • B. Oddity
  • C. Coincidence
  • D. Impossibility

Answer: A

NEW QUESTION 5
Inferential Statistics is largely about Significance. There are both Practical and __________ Significance to consider during an analysis of data in a Lean Six Sigma project.

  • A. Problematic
  • B. Impractical
  • C. Usable
  • D. Statistical

Answer: D

NEW QUESTION 6
The Central Limit Theorem helps us understand the __________ we are taking and is the basis for using sampling to estimate population parameters.

  • A. Analysis
  • B. Kurtosis
  • C. Risk
  • D. Route

Answer: C

NEW QUESTION 7
For a Normal Distribution the Mean, Median and Mode are the same data point.

  • A. True
  • B. False

Answer: A

NEW QUESTION 8
The practice of utilizing Poka-Yoke is also known as __________.

  • A. Thorough integration
  • B. Mistake proofing
  • C. On site inspection
  • D. Lean controls

Answer: B

NEW QUESTION 9
Which of these is Discrete data?

  • A. Train arrived at 4:17 pm.
  • B. Race car consumed 23 gallons of fuel.
  • C. Of the 42 people on the bus, 12 went into the station.
  • D. It took 3 hours and 32 minutes to complete the marathon.

Answer: C

NEW QUESTION 10
The Standard Deviation for the distribution of Means is called the __________ and approaches zero as the sample size reaches 30.

  • A. Standard Error
  • B. Mean Deviation
  • C. Mean Spread
  • D. Mean Error

Answer: A

NEW QUESTION 11
Hypothesis Testing can save time and help avoid high costs of experimental efforts by using existing data.

  • A. True
  • B. False

Answer: A

NEW QUESTION 12
When a Belt is analyzing sample data she should keep in mind that 95% of Normally Distributed data is within +/- 2 Standard Deviations from the Mean.

  • A. True
  • B. False

Answer: A

NEW QUESTION 13
One of the metrics commonly used in Lean Six Sigma is DPU. This acronym stands for __________.

  • A. Deferred planned usage
  • B. Defects per unit
  • C. Decreased production utilization
  • D. Downtime per unit

Answer: B

NEW QUESTION 14
Cost of Poor Quality (COPQ) can be classified as Tangible (Visible) Costs and Hidden Costs.

  • A. True
  • B. False

Answer: A

NEW QUESTION 15
After reviewing the Capability Analysis shown here select the statement(s) that are untrue.

  • A. The process is properly assumed to be a Normal process
  • B. The Mean of the process moving range is 1.78
  • C. The process is out of Control
  • D. This Capability Analysis used subgroups
  • E. Majority of the dimensional values are outside of the tolerance than within

Answer: A

NEW QUESTION 16
A process can be defined as a repetitive and systematic series of steps or activities where inputs are modified or assembled to achieve a customer desired result.

  • A. True
  • B. False

Answer: A

NEW QUESTION 17
Significant variation in process performance is a consequence of several causes that can be classified using which of the terminologies shown. (Note: There are 2 correct answers).

  • A. Common
  • B. Random
  • C. Uneducated
  • D. Special
  • E. Vital

Answer: AD

NEW QUESTION 18
Lean had its origins in the development and practice of the __________ Production System.

  • A. Honda
  • B. Toyota
  • C. Ford
  • D. Motorola

Answer: B

NEW QUESTION 19
What is the Cycle Time, in seconds, for a process having a Throughput of 7,200 units per hour?

  • A. 0.5
  • B. 2
  • C. 4
  • D. 10

Answer: A

NEW QUESTION 20
Measurement System Analysis is a procedure used to quantify variation of the method or system used for taking measurements.

  • A. True
  • B. False

Answer: A