How Many Questions Of CSM-001 Question
Our pass rate is high to 98.9% and the similarity percentage between our CSM-001 study guide and real exam is 90% based on our seven-year educating experience. Do you want achievements in the GAQM CSM-001 exam in just one try? I am currently studying for the GAQM CSM-001 exam. Latest GAQM CSM-001 Test exam practice questions and answers, Try GAQM CSM-001 Brain Dumps First.
Free CSM-001 Demo Online For GAQM Certifitcation:
NEW QUESTION 1
How should the Product Backlog arranged?
- A. Product Backlog items should be sorted by level of effort or complexity in descending order.
- B. Product Backlog items should be sorted by business priority in descending order.
- C. Product Backlog items should be date sorted in ascending order.
- D. Product Backlog items should be grouped by business category or feature.
Answer: B
NEW QUESTION 2
Which of the following is NOT part of the Sprint?
- A. The product is released to customers after each Sprint
- B. The principal goal for a Sprint is to produce release-quality increments in functionality
- C. Releases usually incorporate the result of multiple Sprints
- D. Occur at times dictated by customer and business needs
Answer: A
NEW QUESTION 3
What are the four stages of team development?
- A. Formin
- B. Stormin
- C. Normin
- D. Performing
- E. Lo
- F. Mediu
- G. High
- H. Developin
- I. Shapin
- J. Finishing
- K. Gatherin
- L. Buildin
- M. Developin
- N. Educating
Answer: A
NEW QUESTION 4
Select which option best completes the following statement: _______ is all about response to change.
- A. Change management
- B. Planning
- C. Customer satisfaction
- D. Agile
Answer: D
NEW QUESTION 5
Under what circumstances should separate Product Backlogs be maintained?
- A. There are several Product Owners for one produc
- B. Each Product Owner should have their own Product Backlog
- C. There are multiple teams working on independent product
- D. Each unique combination of team and product should have an independent Product Backlog
- E. There are multiple product features being developed by the same team.
- F. There are multiple teams working on the components of the same produc
- G. Each team should an independent Product Backlog
Answer: B
NEW QUESTION 6
Which of the following statements best describes Product Backlog items?
- A. Undefined or poorly defined Product Backlog items should be placed on the Product Backlog with a low priority
- B. All Product Backlog items are the result of a(n) analysis, requirements and/or design phase(s).
- C. Undefined or poorly defined Product Backlog items should be kept out from the Product Backlog until sufficient detail is known.
- D. Every Product Backlog item, whether low priority or high priority, should possess sufficient detail for the Team to complete in a Sprint.
Answer: C
NEW QUESTION 7
What is the recommended size for a Development Team?
- A. 6, +3 or -3
- B. 9
- C. 6
- D. 7, +2 or -2
Answer: A
NEW QUESTION 8
A line in the Agile Manifesto reads, " _____ and _____ over processes and tools". Please select which option best completes the statement.
- A. Customer; Individuals
- B. People; Relationships
- C. Customers; Employees
- D. Individuals; Interactions
Answer: D
NEW QUESTION 9
According to Scrum, the amount of time for a team to plan Sprint activities is expressed in what unit of time?
- A. Weeks
- B. Months
- C. Hours
- D. Minutes
Answer: C
NEW QUESTION 10
Select which of the following statements is the most accurate.
- A. The Scrum Master is responsible for documenting the Sprint Retrospective discussion.
- B. The Scrum Master is responsible for summarizing the Sprint Retrospective discussion and reporting the discussions to Senior Management.
- C. The Product Owner is responsible for summarizing the Sprint Retrospective discussionand reporting the discussions to Senior Management.
- D. The Scrum Master is responsible for facilitating and participating in the Sprint Retrospective
Answer: D
NEW QUESTION 11
The ______ control model requires that every piece of work be completely understood.
- A. Defined process
- B. Empirical Process
- C. Incremental Process
- D. Six Sigm
- E. Process)
Answer: B
NEW QUESTION 12
What is the primary responsibility of the Scrum Master?
- A. To Prioritize the Product Backlog
- B. To remove any impediments the Development Team encounters during their work
- C. To work with the Product Owner to develop the Product Backlog
- D. To manage the Development Team
Answer: B
NEW QUESTION 13
The individual, detailed pieces of work that are needed to convert a product backlog item into a working software component or solution are called:
- A. User Stories
- B. Use cases
- C. Line items
- D. Tasks
Answer: D
NEW QUESTION 14
How many hours per day should a person on a Scrum team work?
- A. A sustainable pace, usually from 7-8 hours per day.
- B. An "ideal day" measuring only when he or she is productive.
- C. However many hours are needed to get the work done.
- D. 14 hour
Answer: A
NEW QUESTION 15
The most encouraged time of day to hold a Scrum Daily Meeting is:
- A. A beginning of the day
- B. Immediately after lunch
- C. 4:30 PM
- D. 7:00 PM
Answer: A
NEW QUESTION 16
_____ constitute the Sprint Backlog and are often estimated in hours?
- A. User Stories
- B. Use Cases
- C. Features
- D. Tasks
Answer: D
NEW QUESTION 17
You are the Scrum Master. The Sprint will complete in two days. Each day of the Sprint is equivalent to 8 hours. The team has just enough time to complete all tasks in the remaining 16 hours with the exception of three tasks. Of these three tasks, two tasks (a total of 6 hours) are required to complete one Product Backlog item and one task (an estimate of 2 hours) is required to complete another Product Backlog item. How should the development team handle the remaining three tasks?
- A. The development team should negotiate with the Product Owner on the definition of "done".
- B. The development team should work the extra 8 hours to complete their commitment to the Product Owner
- C. The development team should place the two Product Backlog items back onto the Product Backlog
- D. The development team should keep the three tasks on the Sprint Backlog for the next Sprint and complete those tasks first
Answer: A
NEW QUESTION 18
What is the maximum duration of each Sprint planning meeting section?
- A. 1 hour
- B. 30 minutes
- C. 4 hours
- D. 2 hours
- E. 15 minutes
Answer: C
NEW QUESTION 19
Which objectives are covered as part of Sprint Planning?
- A. Understanding what functionality the Product Owner desires within the next Sprint and figuring out how to do it.
- B. Updating the scope of the release with all Sprints, end dates, and costs
- C. Reviewing current functionality that binds the software solution
- D. Recalculating empirical velocity, adjusting team capacity accordingly, and projecting end dates
Answer: A
NEW QUESTION 20
Which of the following are artifacts associated with Scrum?
- A. Product specification
- B. Effort chart
- C. Sprint backlog
- D. Product owner list
Answer: C
NEW QUESTION 21
Which statement below best describes the primary objective of the Sprint Review?
- A. The primary objective of the Sprint Review is to demo the Sprint work for Senior Management
- B. The primary objective of the Sprint Review is to demo the Sprint work and to receive feedback from the Product Owner(s) on the work completed in the Sprint
- C. The primary objective of the Sprint Review is to demo the Sprint work and to receive feedback from the Scrum Mater on the work completed in the Sprint
- D. The primary objective of the Sprint Review is to demo the Sprint work and to recommend ways to work better in the Sprint.
Answer: B
NEW QUESTION 22
Who determines whether the development team has been assigned enough work in a Sprint?
- A. The Development Team
- B. The Product Owner
- C. The Product Owner and the Scrum Master
- D. The Scrum Master
Answer: A
NEW QUESTION 23
When is the Sprint Backlog created?
- A. At the beginning of the project
- B. Prior to the Sprint Planning meeting
- C. During the Sprint
- D. During the Sprint Planning meeting
Answer: B
NEW QUESTION 24
Which three activities will a Product Owner likely engage in during a Sprint?
- A. Run the daily Scrum
- B. Answer questions from the Development Team about items in the current Sprint
- C. Update the Sprint burndown chart
- D. Work with the stakeholders
- E. Prioritize the Development Team's activities.
- F. Provide feedback
Answer: BDF
NEW QUESTION 25
......
Recommend!! Get the Full CSM-001 dumps in VCE and PDF From DumpSolutions.com, Welcome to Download: https://www.dumpsolutions.com/CSM-001-dumps/ (New 112 Q&As Version)