We provide real PMI-001 exam questions and answers braindumps in two formats. Download PDF & Practice Tests. Pass PMI PMI-001 Exam quickly & easily. The PMI-001 PDF type is available for reading and printing. You can print more and practice many times. With the help of our PMI PMI-001 dumps pdf and vce product and material, you can easily pass the PMI-001 exam.

Free PMI-001 Demo Online For PMI Certifitcation:

NEW QUESTION 1
Who is responsible for developing the project management plan and all related component plans?

  • A. Project team
  • B. Portfolio manager
  • C. Project manager
  • D. Project management office

Answer: C

NEW QUESTION 2
Documented identification of a flaw in a project component together with a recommendation is termed a:

  • A. corrective actio
  • B. preventive actio
  • C. non-conformance report,
  • D. defect repai

Answer: D

NEW QUESTION 3
Which type of estimating can produce higher levels of accuracy, depending upon the sophistication and underlying data built into the model?

  • A. Bottom-up
  • B. Three-point
  • C. Parametric
  • D. Analogous

Answer: C

NEW QUESTION 4
What is the total float of the critical path?

  • A. Can be any number
  • B. Zero or positive
  • C. Zero or negative
  • D. Depends on the calendar

Answer: C

NEW QUESTION 5
Which statement correctly describes the value of a business case?

  • A. It provides the necessary information to determine if a project is worth the required investmen
  • B. It provides for alternative dispute resolution procedures in event of contract defaul
  • C. It offers one of several alternative scenarios which assist in performing qualitative risk analysi
  • D. It is used to help a project manager understand the scope of commercial advantage

Answer: A

NEW QUESTION 6
An input to the Identify Risks process is the:

  • A. Risk registe
  • B. Risk probability and impact assessmen
  • C. Communications management pla
  • D. Risk management pla

Answer: D

NEW QUESTION 7
An associate who calculates fees daily to support the department is doing which of the following?

  • A. Phase work
  • B. Project work
  • C. Lifecycle work
  • D. Operations work

Answer: D

NEW QUESTION 8
Fast tracking is a schedule compression technique used to shorten the project schedule without changing project scope. Which of the following can result from fast tracking?

  • A. The risk of achieving the shortened project time is increase
  • B. The critical path will have positive total floa
  • C. Contingency reserves are released for redeployment by the project manage
  • D. Duration buffers are added to maintain a focus on planned activity duration

Answer: A

NEW QUESTION 9
An effective technique for resolving conflict that incorporates multiple viewpoints from differing perspectives to achieve consensus and commitment is:

  • A. smooth/accommodat
  • B. force/direct,
  • C. collaborate/problem solve,
  • D. compromise/reconcil

Answer: C

NEW QUESTION 10
After Define Activities and Sequence Activities, the next process is:

  • A. Estimate Activity Resource
  • B. Estimate Activity Durations,
  • C. Develop Schedul
  • D. Control Schedul

Answer: A

NEW QUESTION 11
What is a tool to improve team performance?

  • A. Staffing plan
  • B. External feedback
  • C. Performance reports
  • D. Co-location

Answer: D

NEW QUESTION 12
Which of the following is a schematic display of the project’s schedule activities and the logical relationships among them?

  • A. Gantt chart
  • B. Project schedule network diagram
  • C. Project milestone list
  • D. Activity list

Answer: B

NEW QUESTION 13
Which of the following is an output of the Plan Quality process?

  • A. Project document update
  • B. Control chart
  • C. Cost performance baseline
  • D. Organizational process asset update

Answer: A

NEW QUESTION 14
Which organizational process assets update is performed during the Close Procurements process?

  • A. Procurement audit
  • B. Lessons learned
  • C. Performance reporting
  • D. Payment requests

Answer: B

NEW QUESTION 15
Identify Risks is part of which Process Group?

  • A. Planning
  • B. Executing
  • C. Closing
  • D. Initiating

Answer: A

NEW QUESTION 16
While processes in the Planning Process Group seek to collect feedback and define project documents to guide project work, organizational procedures dictate when the project planning:

  • A. end
  • B. begin
  • C. delay
  • D. deviate

Answer: A

NEW QUESTION 17
Which tool or technique measures performance of the project as it moves from project initiation through project closure?

  • A. Resource leveling
  • B. Parametric measuring
  • C. Pareto chart
  • D. Earned value

Answer: D

NEW QUESTION 18
The probability and impact matrix is primarily used to:

  • A. Quantify risk issues for trends during a quality audi
  • B. Develop a risk register for risk plannin
  • C. Evaluate each risk’s importance and priority during Perform Qualitative Risk Analysi
  • D. Define risk and compare impacts during Perform Quantitative Risk Analysi

Answer: C

NEW QUESTION 19
......

P.S. Easily pass PMI-001 Exam with 918 Q&As Dumps-hub.com Dumps & pdf Version, Welcome to Download the Newest Dumps-hub.com PMI-001 Dumps: https://www.dumps-hub.com/PMI-001-dumps.html (918 New Questions)