Practical PRINCE2-Exams PRINCE2-Foundation Pdf Online
we provide Actual PRINCE2-Exams PRINCE2-Foundation sample question which are the best for clearing PRINCE2-Foundation test, and to get certified by PRINCE2-Exams PRINCE2 Foundation exam. The PRINCE2-Foundation Questions & Answers covers all the knowledge points of the real PRINCE2-Foundation exam. Crack your PRINCE2-Exams PRINCE2-Foundation Exam with latest dumps, guaranteed!
Also have PRINCE2-Foundation free dumps questions for you:
NEW QUESTION 1
In what product should the quality criteria for a specialist product be recorded?
- A. Quality Management Strategy
- B. Quality Register
- C. Product Description
- D. Project Product Description
Answer: C
NEW QUESTION 2
Which is NOT represented by one of the three primary categories of stakeholder identified in PRINCE2?
- A. Those with a financial interest in the project
- B. Those who will manage the project on a day-to-day basis
- C. Those who will specify the desired outputs of the project
- D. Those who will create the project's outputs
Answer: B
NEW QUESTION 3
Which does a Project Manager produce to define and control the work to be done?
- A. Configuration Item Record
- B. Stage scope tolerance
- C. Team Plan
- D. Work Package
Answer: D
NEW QUESTION 4
Which is a responsibility of a risk owner?
- A. Identify risks to the project that might occur in their department
- B. Own and authorize theuse of the risk budget to fund risk responses
- C. Manage, monitor and control all aspects of an assigned risk
- D. Determine project risk appetite
Answer: C
NEW QUESTION 5
Identify the missing word in the following sentence, A purpose of the [?] theme is to control any unacceptable deviations from the project's objectives.
- A. Change
- B. Plans
- C. Progress
- D. Risk
Answer: C
NEW QUESTION 6
When are tolerances for a Work Package agreed?
- A. When acceptinga Work Package
- B. As work on each product within the Work Package begins
- C. Once ail products have been developed and approved
- D. When the Stage Plan is authorized by the Project Board
Answer: A
NEW QUESTION 7
Which is a true statement about time-driven controls?
- A. Time-driven controls are used for monitoring the progress of Work Packages and management stages
- B. Time-driven controls take place when specific events happen
- C. Time-driven controls are produced at the end of a stage
- D. An Exception Report is a time-driven control
Answer: A
NEW QUESTION 8
Which is a purpose of a Project Brief?
- A. Enable the assembly of the project mandate
- B. Describe the reporting requirements of the various layers of management involved with the project
- C. Describe how changes to products will be controlled
- D. Provide a solid basis for the initiation of the project
Answer: D
NEW QUESTION 9
Which is the Issue Register NOT used for?
- A. Capture external events that are impacting a stage
- B. Record information about a deviation in stage tolerance
- C. Capture any threats or opportunities that might have an impact on astage
- D. Record any problems identified when authorizing a Work Package
Answer: C
NEW QUESTION 10
Which of the following statements about customer's quality expectations and acceptance criteria are true?
1. Customer's quality expectations form a specific and precise list of Acceptance criteria are often expressed in broad terms as a means to gain common understanding of general quality requirements.
2. Measurable criteria that a project product should meet in order to be acceptable to key
stakeholders,
- A. Only 1 is true
- B. Only 2 is true
- C. Both 1 and 2 are true
- D. Neither 1 or 2 are true
Answer: D
NEW QUESTION 11
Which of the following is NOT a purpose of the Closing a Project process?
- A. Plan the activities required to close a project
- B. Enable a comparison of the original objectives of a project against what was actually achieved
- C. Enable premature closureif the Project Board request that a project should no longer continue
- D. Provide a fixed point at which acceptance for the project product is confirmed
Answer: A
NEW QUESTION 12
What process provides the information required to decide whether to authorize the delivery of a project?
- A. Directing a Project
- B. Initiating a Project
- C. Managing Product Delivery
- D. Starting up a Project
Answer: B
NEW QUESTION 13
How is a Benefits Review Plan used in the Closing a Project process?
- A. Checked for inclusion of activities to confirm those benefits which cannot be measured until after project closure
- B. To capture the baseline measures against which to assess benefits
- C. To capture side-effects (beneficial or adverse) identified during post-project benefits reviews
- D. To gain approval for the post-project activities and transferresponsibility to corporate or programme management
Answer: A
NEW QUESTION 14
Which does the Executive need to ensure is in place before the project is initiated?
- A. All Work Packages are authorized
- B. An understanding of how the project will contribute to corporate objectives
- C. The Project Plan has been approved
- D. The Project Initiation Documentation is complete
Answer: B
NEW QUESTION 15
Which should be funded by a change budget?
- A. Increase in agreed scope
- B. Initiation stage
- C. Change Authority
- D. Handover activities
Answer: A
NEW QUESTION 16
Why is the Initiating a Project process used?
- A. To decide which project approach is suitable for the project
- B. To fully understand how the project objectives will be achieved before committing significant resources
- C. To produce the required Work Packages
- D. To enable corporate or programme management to give authorization to deliver a project
Answer: B
NEW QUESTION 17
Identify the missing word in the following sentence. The [?] theme defines that the Project Board is responsible for the overall direction and management of the project,
- A. Progress
- B. Plans
- C. Organization
- D. Business Case
Answer: C
NEW QUESTION 18
Which is an objective of the quality review technique?
- A. To baseline a product
- B. To provide a common understanding of what products a project will create
- C. To define the quality methods required within a project
- D. To determine the quality responsibilities of a project team
Answer: A
NEW QUESTION 19
Which describes risk probability?
- A. Level of risks which the project can tolerate before escalating to the Project Board
- B. Probable effect on the project delivering its objectives
- C. Timeframe within which the risk may occur
- D. A measure of the likelihood of the risk occurring
Answer: D
NEW QUESTION 20
Which enables the project's products and all interdependencies to be clearly identified and documented?
- A. Product breakdown structure
- B. Quality Management Strategy
- C. Product-based planning technique
- D. Quality review technique
Answer: C
NEW QUESTION 21
Why is it crucial that the Project Product Description clearly defines acceptance methods?
- A. Enables Project Assurance to authorize quality activities
- B. Defines how all project products will be reviewed and approved
- C. Defines how it will be proven that the completed project product meets the customer's expectations
- D. Provides confirmation that all project products have met their quality criteria
Answer: C
NEW QUESTION 22
During the Managing a Stage Boundary process, what is reviewed and updated to provide the information needed by the Project Board for assessing the continuing viability of the project?
- A. Benefits Review Plan
- B. Product Status Account
- C. Business Case
- D. Project Plan
Answer: C
NEW QUESTION 23
Which of the following statements about the Project Initiation Documentation are true?
1. The Project Initiation Documentation is used to ensure that a sound basis exists exists before the Project Board authorizes a project.
2. The Project Initiation Documentation should be updated at the end of each stage to reflect the current status of a project before the Project Board authorizes a project.
- A. Only 1 is true
- B. Only 2 is true
- C. Both 1 and 2 are true
- D. Neither 1 or 2 are true
Answer: C
NEW QUESTION 24
Which role is part of the Project Board?
- A. Corporate or programme management
- B. Risk owner
- C. Project Manager
- D. Senior Supplier
Answer: D
NEW QUESTION 25
What product should be used to confirm the version number of ail products in a particular stage?
- A. Issue Register
- B. Product Status Account
- C. Product Description
- D. Configuration Item Record
Answer: B
NEW QUESTION 26
Which is a purpose of an Exception Plan?
- A. Show the reason for the tolerance deviation from a Stage Plan or Project Plan
- B. Reduce the number of exception assessments, by agreeing a budget to cover the costs of any requests for change
- C. Identify the actions required to recover from the effect ofa tolerance deviation
- D. Define the changes which are within the scope of the change budget
Answer: C
NEW QUESTION 27
Which statement applies to Stage Plans?
- A. Always have the same duration as the Project Plan
- B. Are produced at the same time as the Project Initiation Documentation
- C. Assist the Project Manager inthe day-to-day running and control of the project
- D. Provide a baseline against which the Project Board monitor overall progress
Answer: C
NEW QUESTION 28
Which should be funded by a change budget?
- A. Increase in agreedscope
- B. Increase in agreed scope
- C. Increase in agreed scope
- D. Handover activities
Answer: A
NEW QUESTION 29
......
Thanks for reading the newest PRINCE2-Foundation exam dumps! We recommend you to try the PREMIUM Thedumpscentre.com PRINCE2-Foundation dumps in VCE and PDF here: https://www.thedumpscentre.com/PRINCE2-Foundation-dumps/ (296 Q&As Dumps)