How Many Questions Of PRINCE2-Foundation Actual Test
Cause all that matters here is passing the PRINCE2-Exams PRINCE2-Foundation exam. Cause all that you need is a high score of PRINCE2-Foundation PRINCE2 Foundation exam exam. The only one thing you need to do is downloading Testking PRINCE2-Foundation exam study guides now. We will not let you down with our money-back guarantee.
Online PRINCE2-Exams PRINCE2-Foundation free dumps demo Below:
NEW QUESTION 1
What should be implemented using a risk budget?
* 1. A request for change
* 2. A contingent plan
* 3. Actions to avoid a risk from occurring
* 4. Responses to dis-benefits
- A. 1 and 2
- B. 2 and 3
- C. 3 and 4
- D. 1 and 4
Answer: A
NEW QUESTION 2
If the Project Board instructs the Project Manager to implement a request for change, which document would contain details of that change?
- A. Checkpoint Report
- B. Highlight Report
- C. Issue Report
- D. Product Status Account
Answer: C
NEW QUESTION 3
What product defines the reporting requirements between the Project Manager and Team Manager?
- A. Project Brief
- B. Product Description
- C. Team Plan
- D. Work Package
Answer: D
NEW QUESTION 4
Which is the first task of PRINCE2's recommended approach to 'defining and analyzing the products'?
- A. Creating a product flow diagram
- B. Writing the product description
- C. Writing a project product description
- D. Documenting the plan
Answer: A
NEW QUESTION 5
How does the project board use the 'manage by stages' principle to control the project?
- A. By approving the project management team
- B. By reviewing project viability at defined intervals
- C. By ensuring that the benefits are managed and controlled
- D. By reviewing previous project closure documentation
Answer: B
Explanation:
Reference
http://prince2.wiki/Manage_by_stages
NEW QUESTION 6
Which does the Executive need to ensure is in place before the project is initiated?
- A. All Work Packages are authorized
- B. An understanding of how the project will contribute to corporate objectives
- C. The Project Plan has been approved
- D. The Project Initiation Documentation is complete
Answer: B
NEW QUESTION 7
Why does the project board review the PID during an end stage assessment?
- A. To confirm that project controls are adequate for the remainder of the project
- B. To notify the commissioning organization that the project has been authorized
- C. To review summarized progress to date and decide what to do next with the project
- D. To ensure that post-project reviews of operational performance are planned
Answer: C
NEW QUESTION 8
Which of the following statements about the Project Initiation Documentation are true?
* 1. The Project Initiation Documentation is used to ensure that a sound basis exists before the Project Board authorizes a project.
* 2. The Project Initiation Documentation should be updated at the end of each stage to reflect the current status of a project.
- A. Only 1 is true
- B. Only 2 is true
- C. Both 1 and 2 are true
- D. Neither 1 or 2 are true
Answer: C
NEW QUESTION 9
Which is a purpose of the 'initiating a project' process?
- A. To ensure the project has a sound basis before asking the project board to authorize the project
- B. To authorize the stage plan for the next management stage of the project
- C. To establish a contract between the project management team and the commissioning organization
- D. To ensure that prerequisites are in place before starting the project
Answer: A
NEW QUESTION 10
Identify the missing words in the following sentence.
The six aspects of project performance to be managed are [ ? ] costs, timescales and scope.
- A. benefits, change, risk,
- B. benefits, quality, risk,
- C. change, quality, risk,
- D. benefits, change, quality,
Answer: B
Explanation:
Reference:
http://prince2.wiki/Introduction:_The_PRINCE2_Foundation_Training_Manual
NEW QUESTION 11
What is an advantage of dividing the project into stages?
- A. Detailed plans can be prepared closer to the time events will take place
- B. the project board can delegate management of the project to team managers
- C. The project can be authorized by the project manager on a stage by stage basis
- D. The project brief can be updated towards the end of each stage
Answer: A
NEW QUESTION 12
Which is a purpose of the Managing a Stage Boundary process?
- A. Provide the Project Board with sufficient information for approving the next stage
- B. Approve the next Stage Plan
- C. Review and close any risks and issues identified during the previous stage
- D. Control the link between the Project Manager and the Team Manager(s)
Answer: A
NEW QUESTION 13
How are team managers involved in tailoring PRINCE2 suit the project?
- A. Team managers are accountable for the tailoring of the work packages
- B. Team managers may advice on tailoring to improve the management of work packages
- C. Team managers should not be involved in tailoring PRINCE2
- D. Team managers should document the tailoring of the work packages
Answer: B
NEW QUESTION 14
If a project is part of a programme, which 'starting up a project' process activities are MOST likely to be
reduced or eliminated?
- A. Appointing the project board and producing the project brief
- B. Planning the initiation stage and appointing the project manager
- C. Producing the additional role descriptions and validating the project product description
- D. Verifying the project approach and capturing previous lessons
Answer: A
Explanation:
Reference
http://prince2.wiki/Starting_Up_a_Project#Activities
NEW QUESTION 15
Who represents the three project interests on a project?
- A. Project manager
- B. Project support
- C. External project stakeholders
- D. Project board
Answer: D
Explanation:
Reference
http://prince2.wiki/Organization#Three_Project_Interests
NEW QUESTION 16
What process ensures focus on the delivery of a stage's products and avoids uncontrolled change?
- A. Directing a Project
- B. Managing a Stage Boundary
- C. Controlling a Stage
- D. Starting up a Project
Answer: C
NEW QUESTION 17
Which is a purpose of an End Project Report?
- A. Identify individuals or groups that need to be told that the project is coming to an end
- B. Review how well the project performed against the Project Initiation Documentation used to authorize it
- C. Identify individuals or groups that are responsible for measuring the expected benefits after the project has closed
- D. Ensure that key project information is archived and made secure
Answer: B
NEW QUESTION 18
Which is a purpose of the 'managing a stage boundary' process?
- A. To enable the project board to approve the continuation of the project
- B. To exercise overall control over the project while delegating day-to-day management
- C. To assign work to be controlled by the team manager
- D. To define the work that needs to be done to deliver the project product
Answer: A
Explanation:
Reference
http://prince2.wiki/Managing_a_Stage_Boundary#Objective
NEW QUESTION 19
Which is a true statement about acceptance criteria?
- A. Acceptance criteria are used to produce the customer's quality expectations
- B. Acceptance criteria are less specific and precise than customer's quality expectations
- C. Once agreed, acceptance criteria CANNOT be changed
- D. Acceptance criteria should be agreed between the customer and the supplier
Answer: D
NEW QUESTION 20
Which two roles are linked by the Managing Product Delivery process?
- A. Corporate or programme management and Project Board
- B. Project Board and Project Manager
- C. Project Manager and Team Manager
- D. Team Manager and external supplier
Answer: C
NEW QUESTION 21
......
P.S. Easily pass PRINCE2-Foundation Exam with 463 Q&As Dumps-files.com Dumps & pdf Version, Welcome to Download the Newest Dumps-files.com PRINCE2-Foundation Dumps: https://www.dumps-files.com/files/PRINCE2-Foundation/ (463 New Questions)