Act now and download your PRINCE2-Exams PRINCE2-Foundation test today! Do not waste time for the worthless PRINCE2-Exams PRINCE2-Foundation tutorials. Download Leading PRINCE2-Exams PRINCE2 Foundation exam exam with real questions and answers and begin to learn PRINCE2-Exams PRINCE2-Foundation with a classic professional.

Free demo questions for PRINCE2-Exams PRINCE2-Foundation Exam Dumps Below:

NEW QUESTION 1

Which PRINCE2 principle is being applied when tolerances are set for the three levels of plan?

  • A. Manage by stages
  • B. Manage by exception
  • C. Continued business justification
  • D. Learn from experience

Answer: A

Explanation:
Reference https://www.whatisprince2.net/prince2-theme-plans.php

NEW QUESTION 2

Which product identifies the management stages and timescales of a project?

  • A. Project Brief
  • B. Project Product Description
  • C. Project Plan
  • D. Initiation Stage Plan

Answer: C

NEW QUESTION 3

Which is a difference between management and technical stages?

  • A. Management stages require planning and technical stages do not
  • B. Technical stages can overlap and management stages cannot
  • C. Management stages deliver products and technical stages do not
  • D. Technical stages require resources and management stages do not

Answer: B

NEW QUESTION 4

What process provides information on a team’s work to the project manager?

  • A. Controlling a stage
  • B. Directing a project
  • C. Managing a stage boundary
  • D. Managing product delivery

Answer: D

NEW QUESTION 5

Which are reasons for a benefits management approach?
* 1. To state how improvements will be measured
* 2. To confirm that the benefits are realized
* 3. To estimate the costs of improvement
* 4. To define the reason for delivering the improvement

  • A. 1 and 2
  • B. 2 and 3
  • C. 3 and 4
  • D. 1 and 4

Answer: AB

NEW QUESTION 6

What should the 'managing product delivery' process ensure?
* 1. That the planned products meet their quality criteria
* 2. That the stage plan is kept up to date
* 3. That the project board is provided with progress information
* 4. That the planned products are delivered within tolerance

  • A. 1 and 2
  • B. 2 and 3
  • C. 3 and 4
  • D. 1 and 4

Answer: C

Explanation:
Reference
http://prince2.wiki/Managing_Product_Delivery

NEW QUESTION 7

Identify the missing word(s) in the following sentence.
The 'controlling a stage' process is used to manage and control each [ ? ] of a project.

  • A. delivery step
  • B. benefit
  • C. delivery stage
  • D. team plan

Answer: C

NEW QUESTION 8

Which is a purpose of the 'closing a project' process?

  • A. To provide the project board with information to judge the success of a stage
  • B. To confirm the project has nothing more to deliver
  • C. To establish mechanisms to judge whether the project is still viable
  • D. To establish mechanisms for forecasting project objectives

Answer: B

Explanation:

Reference
http://prince2.wiki/Closing_a_Project#Objective

NEW QUESTION 9

Where should a team manager look for information about the quality required for a product?

  • A. Project initiation documentation
  • B. Product description
  • C. Team plan
  • D. Quality management approach

Answer: B

Explanation:

Reference
http://prince2.wiki/Quality#The_Quality_Knowledge_provided_by_PRINCE2

NEW QUESTION 10

What theme provides all management levels within the project management team with mechanisms for monitoring and control?

  • A. Progress
  • B. Change
  • C. Organization
  • D. Quality

Answer: A

NEW QUESTION 11

Which product records any project outcomes perceived as negative by stakeholders?

  • A. Business Case
  • B. Project Plan
  • C. Communication Management Strategy
  • D. Project Product Description

Answer: A

NEW QUESTION 12

Which process ensures focus on the delivery of a stage's products and avoids uncontrolled change?

  • A. Directing a project
  • B. Managing a stage boundary
  • C. Controlling a stage
  • D. Starting up a project

Answer: C

Explanation:
Reference
https://www.greycampus.com/opencampus/prince-2-foundation/introduction-on-controlling-a-stage-process-in-p

NEW QUESTION 13

What is an advantage of applying the 'learn from experience' principle?

  • A. It allows the project board to delegate cost tolerances to the project manager
  • B. It allows the project team to fully understand their roles and responsibilities
  • C. It allows the project manager to delegate time tolerances to the team managers
  • D. It allows the project team to identify improvements to be made during the project

Answer: D

NEW QUESTION 14

What product would enable the Project Manager to review how a Work Package is performing against its cost tolerance?

  • A. Configuration Item Record
  • B. Quality Register
  • C. Highlight Report
  • D. Checkpoint Report

Answer: D

NEW QUESTION 15

Identify the missing words in the following sentence.
The 'managing product delivery' process provides a controlled link between [ ? ] and a project manager.

  • A. project assurance
  • B. the project board
  • C. the corporate, programme management or the customer
  • D. a team manager

Answer: D

NEW QUESTION 16

Which is the purpose of the Change theme?

  • A. Prevent change to baselined products
  • B. Identify, assess and control any potential and approved changes to baselined products
  • C. Establish mechanisms to monitor and compare actual achievements against those planned
  • D. Assess and control uncertainty

Answer: B

NEW QUESTION 17

Which statement describes the context of the 'initiating a project" process?

  • A. The project is viewed from the perspective of the project board in this process
  • B. This process should result in key stakeholders being committed to the project
  • C. This process is triggered by the assembly of the project brief
  • D. The 'controlling a stage' process will start immediately after this process

Answer: B

NEW QUESTION 18

Which describes a project benefit?

  • A. A specialist product of the project
  • B. The result of a change derived from using the project's products
  • C. An uncertain result caused by project actions
  • D. A measurable improvement resulting from an outcome

Answer: D

NEW QUESTION 19

Which process is used to define how baselines will be established and controlled?

  • A. Controlling a stage
  • B. Directing a project
  • C. Initiating a project
  • D. Starting up a project

Answer: D

Explanation:

Reference
http://prince2.wiki/Quality

NEW QUESTION 20

Which is an objective of the Initiating a Project process?

  • A. Develop the corporate quality management system as part of the Project Initiation Documentation
  • B. Prepare the plans for the subsequent stages
  • C. Summarize how the organization's project management method will be tailored for the project
  • D. Request authority from corporate management to deliver the project

Answer: C