The Secret Of PRINCE2-Exams PRINCE2-Foundation Test Engine
It is impossible to pass PRINCE2-Exams PRINCE2-Foundation exam without any help in the short term. Come to Exambible soon and find the most advanced, correct and guaranteed PRINCE2-Exams PRINCE2-Foundation practice questions. You will get a surprising result by our Renewal PRINCE2 Foundation exam practice guides.
Free PRINCE2-Foundation Demo Online For PRINCE2-Exams Certifitcation:
NEW QUESTION 1
What is the definition of a project outcome?
- A. A measurable improvement that is perceived as an advantage by one or more stakeholders
- B. The reason for the project
- C. The result of the change derived from using the project's outputs
- D. The project's specialist products.
Answer: C
NEW QUESTION 2
Which process provides the Project Board with sufficient information for it to review the success of a completed stage and confirm continued business justification?
- A. Controlling a Stage
- B. Closing a Project
- C. Directing a Project
- D. Managing a Stage Boundary
Answer: D
NEW QUESTION 3
Which is a step in the recommended approach to 'defining and analyzing the products'?
- A. Preparing estimates
- B. Designing a plan
- C. Writing a project product description
- D. Identifying activities and dependencies
Answer: B
Explanation:
Reference http://prince2.wiki/Plans
NEW QUESTION 4
Which is a minimum requirement when applying the 'risk' theme?
- A. To identity and ring-fence an explicit risk budget within the project's budget
- B. To describe the probability impact grid in the risk management approach
- C. To appoint project assurance to maintain the risk register during initiation
- D. To assess if risks might have a material impact on business justification
Answer: D
NEW QUESTION 5
Which theme verifies that a project's products are fit for purpose?
- A. Business case
- B. Organization
- C. Quality
- D. Progress
Answer: C
Explanation:
Reference
http://prince2.wiki/Quality
NEW QUESTION 6
Which describes an off-specification?
- A. An interdependency between products that was previously unidentified
- B. The addition of an improvement to a product description
- C. A prototype demonstrating a possible design solution
- D. The production of more than the defined quantity of a specialist product
Answer: A
Explanation:
Reference https://www.prince2primer.com/prince2-change-control/
NEW QUESTION 7
Which product identifies how often stakeholders require information?
- A. Communication management approach
- B. Quality management approach
- C. Change control approach
- D. Risk management approach
Answer: A
Explanation:
Reference
http://prince2.wiki/Communication_Management_Strategy_Template#Content_of_the_Communication_Manag
NEW QUESTION 8
Which is an objective of the Closing a Project process?
- A. Prepare the plan for the next stage
- B. Assess any benefits that have already been realized
- C. Produce a Benefits Review Plan to identify what benefits are expected
- D. Check that all benefits are realized before closing a project
Answer: B
NEW QUESTION 9
Which is a purpose of the Starting up a Project process?
- A. Provide information so a decision can be made as to whether a project is viable and worthwhile to initiate
- B. Define the means of communication between the project and corporate or programme management
- C. Define the project controls
- D. Record any identified risks in the Risk Register
Answer: A
NEW QUESTION 10
In which product does a Project Manager define the time and cost tolerances for the work to be done by a Team Manager?
- A. Product Description
- B. Team Plan
- C. Work Package
- D. Stage Plan
Answer: C
NEW QUESTION 11
Which risk response type is appropriate to respond to an opportunity?
- A. Accept
- B. Fallback
- C. Exploit
- D. Transfer
Answer: C
NEW QUESTION 12
Which is an objective of the Closing a Project process?
- A. Review and approve the plan for project closure
- B. Review the performance of the project against its baseline
- C. Perform any post-project reviews
- D. Create a Benefits Review Plan
Answer: B
NEW QUESTION 13
Which is a purpose of a quality register?
- A. To record the quality management approach for a product
- B. To issue a unique reference number for each product
- C. To detail the number and type of quality activities to be conducted
- D. To identify corrective actions that are required after an audit by quality assurance
Answer: C
Explanation:
Reference
http://prince2.wiki/Quality#The_Quality_Register
NEW QUESTION 14
Which is an objective of the Managing Product Delivery process?
- A. Sign-off completed Work Packages
- B. Ensure the Business Case is kept under review
- C. Report progress to the Project Board
- D. Ensure that work on products is authorized and agreed with the team
Answer: D
NEW QUESTION 15
Which management level should approve a course of action if project-level tolerance is exceeded?
- A. Corporate, programme management or the customer
- B. Project board
- C. Project manager
- D. Team manager
Answer: A
NEW QUESTION 16
Which process has the objective of confirming that acceptance criteria have been met?
- A. Controlling a stage
- B. Directing a project
- C. Managing product delivery
- D. Closing a project
Answer: D
NEW QUESTION 17
Which of the following can be done to control the size of the Project Board on a project that involves multiple users and suppliers?
- A. Create a separate Project Board to manage the supplier elements of the project
- B. Create multiple smaller Project Boards during the process of Starting up a Project, one for each of the project's stages.
- C. Create user and supplier groups
- D. Appoint corporate quality assurance to perform the Project Assurance role for all members of the Project Board
Answer: C
NEW QUESTION 18
What information should be recorded in the quality register?
- A. Planned activities to determine whether the products are fit for purpose
- B. Potential threats to the project's objectives and how they will be managed
- C. Lessons that the project will capture and use during the project
- D. Off-specifications that will occur during the project
Answer: C
Explanation:
Reference https://mplaza.pm/prince2-quality-register-template/
NEW QUESTION 19
Which is a key decision made during the 'directing a project' process?
- A. Select and appoint the project executive
- B. Approve the project manager role description
- C. Confirm that the benefits management approach addresses all expected benefits
- D. Approve the proposed project mandate
Answer: B
Explanation:
Reference
https://www.greycampus.com/opencampus/prince-2-practitioner/purpose-of-directing-a-project-process-in-princ
NEW QUESTION 20
Which is a true statement about PRINCE2 event-driven controls?
- A. Event-driven controls take place at predefined periodic intervals
- B. Event-driven controls are produced at the frequency defined in a Work Package
- C. Event-driven controls are used for decision making
- D. Checkpoint Reports are event-driven controls
Answer: C
NEW QUESTION 21
......
Thanks for reading the newest PRINCE2-Foundation exam dumps! We recommend you to try the PREMIUM Dumpscollection.com PRINCE2-Foundation dumps in VCE and PDF here: https://www.dumpscollection.net/dumps/PRINCE2-Foundation/ (463 Q&As Dumps)