Proper study guides for Update PRINCE2-Exams PRINCE2 Foundation exam certified begins with PRINCE2-Exams PRINCE2-Foundation preparation products which designed to deliver the Real PRINCE2-Foundation questions by making you pass the PRINCE2-Foundation test at your first time. Try the free PRINCE2-Foundation demo right now.
PRINCE2-Exams PRINCE2-Foundation Free Dumps Questions Online, Read and Test Now.
NEW QUESTION 1
Which is the Issue Register NOT used for?
- A. Capture external events that are impacting a stage
- B. Record information about a deviation in stage tolerance
- C. Capture any threats or opportunities that might have an impact on a stage
- D. Record any problems identified when authorizing a Work Package
Answer: C
NEW QUESTION 2
From whom does a Team Manager obtain approval for a completed product?
- A. Project Manager
- B. Project Support
- C. The authority defined in the Product Description
- D. Senior Supplier
Answer: C
NEW QUESTION 3
Which project management team member represents the interest of those who will operate the project's products to realize the benefits after the project is complete?
- A. Executive
- B. Senior User
- C. Senior Supplier
- D. Project Manager
Answer: B
NEW QUESTION 4
Which should be provided by a project mandate?
- A. Terms of reference
- B. Detailed Business Case
- C. Stage tolerances
- D. Initiation Stage Plan
Answer: A
NEW QUESTION 5
What process is used by the Project Manager to maintain focus on delivery of a stage's products within agreed tolerances?
- A. Directing a Project
- B. Controlling a Stage
- C. Managing a Stage Boundary
- D. Managing Product Delivery
Answer: B
NEW QUESTION 6
Identify the missing word in the following sentence. The risk response type [ ? ] can be used to respond to a threat and an opportunity.
- A. Avoid
- B. Reduce
- C. Share
- D. Transfer
Answer: C
NEW QUESTION 7
Which is a minimum requirement for applying the quality theme?
- A. To define the project's approach to quality control
- B. To undertake independent audits of the project throughout the project
- C. To apply the recommended quality review technique
- D. To define the project's approach to quality assurance
Answer: A
NEW QUESTION 8
Who should use the information in a Lessons Report to refine, change and improve the standards within a quality management system?
- A. Corporate group
- B. Project Board
- C. Project Assurance
- D. Executive
Answer: A
NEW QUESTION 9
Which is a purpose of the change theme?
- A. To prevent change to baselined products
- B. To identify, assess and control any potential and approved changes to baselined products
- C. To establish mechanisms to monitor and compare actual achievements against those planned
- D. To assess and control uncertainty
Answer: B
Explanation:
Reference
https://www.greycampus.com/opencampus/prince-2-foundation/introduction-on-prince2-change-theme
NEW QUESTION 10
Which is a factor when deciding the duration of a management stage?
- A. The work packages to be delivered
- B. The level of risk in the project
- C. The cost of the stage
- D. The number of products to be produced in the project
Answer: B
Explanation:
Reference https://www.prince2primer.com/the-design-of-prince2-management-stages/
NEW QUESTION 11
Why is the Initiating a Project process used?
- A. To decide which project approach is suitable for the project
- B. To fully understand how the project objectives will be achieved before committing significant resources
- C. To produce the required Work Packages
- D. To enable corporate or programme management to give authorization to deliver a project
Answer: B
NEW QUESTION 12
Which does NOT reflect the PRINCE2 principle of continued business justification?
- A. There must be a justifiable reason for starting a project
- B. The business justification drives decision making
- C. If a project is no longer forecast to deliver a financial benefit, it should be stopped.
- D. If a project can no longer be justified, it should be stopped
Answer: C
NEW QUESTION 13
Which is an assumption about the PRINCE2 customer/supplier environment?
- A. The supplier will pay for the project
- B. The customer will provide the resources to deliver the products
- C. The customer will specify the desired result
- D. The supplier will tailor the project's application of PRINCE2
Answer: C
NEW QUESTION 14
Which is a purpose of a Project Product Description?
- A. Records the costs and timescales for delivery of the project's final product
- B. Shows the dependencies between the project's products to aid planning
- C. Provides a list of all the products to be delivered by the project
- D. Defines what the project must deliver in order to gain acceptance
Answer: D
NEW QUESTION 15
Which is a purpose of the Risk Register?
- A. Describe the risk management techniques and standards to be applied to the project
- B. Act as a central record of information relating to the identified risks for the project
- C. Act as a repository for informal issues
- D. List the responsibilities for achieving an effective risk management procedure
Answer: B
NEW QUESTION 16
What should the benefits management approach define?
- A. What actions will be taken to ensure the project's outcomes are achieved
- B. What will be used to record the effectiveness of the project's approaches
- C. How the project has progressed against its plans
- D. The suitability of the project management team structure
Answer: C
NEW QUESTION 17
Which are benefits of using PRINCE2?
* 1. It removes the need for activity-based planning
* 2. It promotes learning and continuous improvement
* 3. It can be applied to any type of project
* 4. It defines specific leadership and other interpersonal skills required
- A. 1 and 2
- B. 2 and 3
- C. 3 and 4
- D. 1 and 4
Answer: B
Explanation:
Reference https://www.axelos.com/best-practice-solutions/prince2/key-benefits-of-prince2
NEW QUESTION 18
Which is an objective of the Directing a Project process?
- A. Create and authorize the project mandate
- B. Provide management control and direction
- C. Control the day-to-day running of the project
- D. Provide accurate progress information to the Project Manager
Answer: B
NEW QUESTION 19
What product is used to maintain a record of those who have an interest in the project and their information requirements?
- A. Project Plan
- B. Communication Management Strategy
- C. Project Brief
- D. Project Product Description
Answer: B
NEW QUESTION 20
Which is a purpose of the 'directing a project' process?
- A. To exercise overall control over the project
- B. To take corrective action to control risks and issues
- C. To do the minimum in order to decide whether the project is feasible
- D. To update the project plan before the next stage
Answer: A
Explanation:
Reference
http://prince2.wiki/Directing_a_Project#Purpose