NEW QUESTION 1

An input to the Identify Risks process is the:

  • A. Risk register.
  • B. Risk probability and impact assessment.
  • C. Communications management plan.
  • D. Risk management plan.

Answer: D

NEW QUESTION 2

Which input will be used when tasked with developing the human resource plan?

  • A. Project management plan
  • B. Activity resource requirements
  • C. Resource calendar
  • D. Project staff assignments

Answer: B

NEW QUESTION 3

Which stakeholder communicates with higher levels of management to gather organizational support and promote project benefits?

  • A. Portfolio manager
  • B. Project sponsor
  • C. Project manager
  • D. Project management office

Answer: B

NEW QUESTION 4

Which of the following processes includes prioritizing risks for subsequent further analysis or action by assessing and combining their probability of occurrence and impact?

  • A. Qualitative risk analysis
  • B. Quantitative risk analysis
  • C. Risk management planning
  • D. Risk response planning

Answer: A

NEW QUESTION 5

The Monitoring and Controlling Process Group includes processes that:

  • A. Establish the scope, objectives, and course of action of a project,
  • B. Define a new project or a new phase of an existing project.
  • C. Track, review, and regulate the progress and performance of a project.
  • D. Complete the work defined in the project management plan.

Answer: C

NEW QUESTION 6

Which of the following is a conflict resolution technique that emphasizes areas of agreement rather than areas of difference?

  • A. Compromising
  • B. Collaborating
  • C. Smoothing
  • D. Problem Solving

Answer: C

NEW QUESTION 7

Technical capability, past performance, and intellectual property rights are examples of:

  • A. performance measurement criteria
  • B. source selection criteria
  • C. product acceptance criteria
  • D. phase exit criteria

Answer: B

NEW QUESTION 8

Which Activity Duration Estimating technique incorporates additional timing for contingency purposes?

  • A. Analogous Estimating
  • B. Expert Judgment
  • C. Optimistic Estimates
  • D. Reserve Analysis

Answer: D

NEW QUESTION 9

Managing ongoing production of goods and services to ensure business continues efficiently describes which type of management?

  • A. Portfolio
  • B. Project
  • C. Program
  • D. Operations

Answer: D

NEW QUESTION 10

Which of the following is an output from Control Scope?

  • A. Change requests
  • B. Variance analysis
  • C. Accepted deliverables
  • D. Requirements documentation

Answer: A

NEW QUESTION 11

What type of reward can hurt team cohesiveness?

  • A. Sole-sum
  • B. Win-lose
  • C. Lose-win
  • D. Partial-sum

Answer: B

NEW QUESTION 12

An input to the Estimate Activity Resources process is:

  • A. Activity resource requirements.
  • B. Published estimating data.
  • C. Resource calendars.
  • D. Resource breakdown structure (RBS).

Answer: C

NEW QUESTION 13

What are the identified risks for doing excessive decomposition in a WBS?

  • A. Insufficient project funding and disqualification of sellers
  • B. Insufficient project funding and ineffective use of resources
  • C. Disqualification of sellers and non-productive management efforts
  • D. Non-productive management effort and inefficient use of resources

Answer: D

NEW QUESTION 14

Budgets reserved for unplanned changes to project scope and cost are:

  • A. Contingency reserves.
  • B. Management reserves.
  • C. Authorized budgets.
  • D. Cost baselines.

Answer: B

NEW QUESTION 15

What quality control tool graphically represents how various elements of a system interrelate?

  • A. Control chart
  • B. Flowchart
  • C. Run chart
  • D. Pareto chart

Answer: B

NEW QUESTION 16

The only Process Group that comprises processes that typically occur from the beginning to the end of the project life cycle is:

  • A. Planning.
  • B. Executing,
  • C. Monitoring and Controlling.
  • D. Closing.

Answer: A

NEW QUESTION 17

Which Perform Quality Assurance tool or technique is used to identify a problem, discover the underlying causes that lead to it, and develop preventative actions?

  • A. Inspection
  • B. Quality audits
  • C. Design of experiments
  • D. Root cause analysis

Answer: D

NEW QUESTION 18

Which tool is used to develop technical details within the project management plan?

  • A. Expert judgment
  • B. Project management methodology
  • C. Project management information system (PMIS)
  • D. Project selection methods

Answer: A

NEW QUESTION 19

Which technique should a project manager use in a situation in which a collaborative approach to conflict management is not possible?

  • A. Coaching
  • B. Avoidance
  • C. Consensus
  • D. Influencing

Answer: B

NEW QUESTION 20

Which knowledge area employs the processes required to ensure timely and appropriate generation, collection, distribution, storage, retrieval, and ultimate disposition of project information?

  • A. Project Risk Management
  • B. Project Integration Management
  • C. Project Communications Management
  • D. Project Quality Management

Answer: C

NEW QUESTION 21

Which of the following is an output of the Information Distribution Process?

  • A. Project calendar
  • B. Communication management plan
  • C. Requested changes
  • D. Communication requirement plan

Answer: C

NEW QUESTION 22

In a weak matrix, the project managers role is:

  • A. part-time
  • B. full-time
  • C. occasional
  • D. unlimited

Answer: A

NEW QUESTION 23

Who is responsible for developing the project management plan and all related component plans?

  • A. Project team
  • B. Portfolio manager
  • C. Project manager
  • D. Project management office

Answer: C

NEW QUESTION 24
......