We provide real PMP exam questions and answers braindumps in two formats. Download PDF & Practice Tests. Pass PMP PMP Exam quickly & easily. The PMP PDF type is available for reading and printing. You can print more and practice many times. With the help of our PMP PMP dumps pdf and vce product and material, you can easily pass the PMP exam.
Online PMP free questions and answers of New Version:
NEW QUESTION 1
If the most likely duration of an activity is five weeks, the best-case duration is two weeks, and the worst-case duration is 14 weeks, how many weeks is the expected duration of the activity?
- A. One
- B. Five
- C. Six
- D. Seven
Answer: C
NEW QUESTION 2
Team performance assessments is an output of which of the following processes?
- A. Develop Human Resource Plan
- B. Perform Quality Control
- C. Develop Project Team
- D. Manage Project Team
Answer: C
NEW QUESTION 3
The correct equation for schedule variance (SV) is earned value:
- A. minus planned value [EV - PV].
- B. minus actual cost [EV - AC].
- C. divided by planned value [EV/PV],
- D. divided by actual cost [EV/AC].
Answer: A
NEW QUESTION 4
PMBOI Guide is a standard that describes:
- A. product-oriented processes.
- B. project management processes.
- C. product-oriented and project management processes.
- D. program management and project management processes.
Answer: B
NEW QUESTION 5
A technique used to determine the cause and degree of difference between baseline and actual performance is:
- A. Product analysis.
- B. Variance analysis.
- C. Document analysis,
- D. Decomposition.
Answer: B
NEW QUESTION 6
Which is a tool or technique used in scope definition?
- A. Templates, forms, and standards
- B. Change requests
- C. Stakeholder analysis
- D. Project assumptions
Answer: C
NEW QUESTION 7
An issue log is an input to which Project Human Resource Management process?
- A. Manage Project Team
- B. Acquire Project Team
- C. Plan Human Resource Management
- D. Develop Project Team
Answer: A
NEW QUESTION 8
The project manager notes that stakeholders are aware of the project and potential impacts and are actively engaged in ensuring that the project is a success. The engagement level of the stakeholders should be classified as:
- A. Supportive
- B. Leading
- C. Neutral
- D. Resistant
Answer: B
NEW QUESTION 9
The cost baseline and project funding requirements are outputs of which process in Project Cost Management?
- A. Estimate Costs
- B. Control Costs
- C. Plan Cost Management
- D. Determine Budget
Answer: D
NEW QUESTION 10
What is the number of stakeholders, if the project has 28 potential communication channels?
- A. 7
- B. 8
- C. 14
- D. 16
Answer: B
NEW QUESTION 11
The Project Management Process Group in which performance is observed and measured regularly from project initiation through completion is:
- A. Executing.
- B. Initiating,
- C. Monitoring and Controlling.
- D. Planning.
Answer: C
NEW QUESTION 12
Using the following data, what is the Schedule Performance Index (SPI)? EV= $500 PV= $750 AC= $1000 BAC= $1200
- A. 0.67
- B. 1.5
- C. 0.75
- D. 0.5
Answer: A
NEW QUESTION 13
Which item is an output of Plan Quality Management and an input to Perform Quality
Assurance?
- A. Organizational process updates
- B. Quality metrics
- C. Change requests
- D. Quality control measurements
Answer: B
NEW QUESTION 14
Stakeholder management strategy is an output of:
- A. Plan Communications.
- B. Distribute Information.
- C. Report Performance.
- D. Identify Stakeholders.
Answer: D
NEW QUESTION 15
What are the Project Procurement Management processes?
- A. Conduct Procurements, Control Procurements, Integrate Procurements, and Close Procurements
- B. Estimate Procurements, Integrate Procurements, Control Procurements, and Validate Procurements
- C. Plan Procurement Management, Conduct Procurements, Control Procurements, and Close Procurements
- D. Plan Procurement Management, Perform Procurements, Control Procurements, and Validate Procurements
Answer: C
NEW QUESTION 16
Which is one of the major outputs of Sequence Activities?
- A. Responsibility assignment matrix (RAM)
- B. Work breakdown structure (WBS) update
- C. Project schedule network diagram
- D. Mandatory dependencies list
Answer: C
NEW QUESTION 17
Which Control Quality tool is also known as an arrow diagram?
- A. Matrix diagram
- B. Affinity diagram
- C. Tree diagram
- D. Activity network diagram
Answer: D
NEW QUESTION 18
Which of the following is a tool and technique used to monitor risk?
- A. Technical performance measurement
- B. Cost performance baseline
- C. Benchmarking
- D. Cost of quality
Answer: A
NEW QUESTION 19
The methodology that combines scope, schedule, and resource measurements to assess project performance and progress is known as:
- A. Earned value management.
- B. Forecasting.
- C. Critical chain methodology.
- D. Critical path methodology.
Answer: A
NEW QUESTION 20
Which of the following is an output of Define Scope?
- A. Project scope statement
- B. Project charter
- C. Project plan
- D. Project schedule
Answer: A
NEW QUESTION 21
An intentional activity to modify a nonconforming product or product component is called:
- A. defect repair
- B. work repair
- C. corrective action
- D. preventive action
Answer: A
NEW QUESTION 22
An input to the Collect Requirements process is the:
- A. stakeholder register.
- B. project management plan.
- C. project scope statement.
- D. requirements management plan.
Answer: A
NEW QUESTION 23
Which of the following are examples of interactive communication?
- A. Intranet sites
- B. Voice mails
- C. Video conferences
- D. Press releases
Answer: C
NEW QUESTION 24
......
Recommend!! Get the Full PMP dumps in VCE and PDF From DumpSolutions.com, Welcome to Download: https://www.dumpsolutions.com/PMP-dumps/ (New 918 Q&As Version)